Before a bridge or a transmission tower rises above the ground, someone has to build what holds it up.
That can mean drilling several metres into solid rock, lowering steel into the hole and filling it with concrete. Once the structure is finished, the work disappears from view.
LTS Mining & Civil Pty. Ltd., ACN 164 598 645, built more than 200 of those foundations for two Queensland electricity transmission lines. On 13 October 2026 the company entered voluntary administration, appointing Lindsay Stephen Bainbridge and Timothy James Bradd of Pitcher Partners as administrators. Creditors meet on 23 October.
Is LTS Mining & Civil in liquidation? No. In a voluntary administration the administrators take control of the company, investigate its position and report to creditors. Creditors then decide its future: a deed of company arrangement, a return to the directors, or liquidation.
For anyone who contracted with LTS, supplied it or hired equipment to it, the question is what was unfinished or unpaid when the administrators took control.
A New South Wales company with a Queensland licence
LTS Mining & Civil was registered on 2 July 2013. The Australian Business Register places its main business location in postcode 2445 on the New South Wales Mid North Coast, and its 2019 website gave an address at Lake Cathie. ASIC's notice records the company as incorporated in Victoria. Its supplier profile lists premises at Yatala, between Brisbane and the Gold Coast.
In Queensland it holds Queensland Building and Construction Commission licence 15595877, for Foundation Work (Piling and Anchors). The licence sits in financial Category 3, which allows annual turnover of up to $30 million. That is a ceiling the licence permits, not a revenue figure.
More than 100 foundations at Coopers Gap
Coopers Gap Wind Farm sits near Cooranga North, between Dalby and Kingaroy. Its electricity reaches the grid along a transmission line, and every structure on that line needs a foundation.
LTS's own project page, as published in 2019, records the company as engaged to build those foundations. The job ran to more than 100 foundations, from 1.5 to 2.5 metres in diameter and up to 9 metres deep, through rock stronger than 150 MPa. In ordinary terms, that is exceptionally hard rock, and LTS described breaking it with drill-and-blast rigs.
The foundations were for the electricity connection, not the wind turbines themselves.
Another 100 at Kennedy Energy Park
At Kennedy Energy Park, near Hughenden in north Queensland, LTS's project page records the foundations for the transmission line to Cape River Substation, and for the substation itself: another 100-plus foundations, 0.45 to 1.5 metres across and up to 9 metres deep, in very high strength rock.

The same project list included the Clarence River bridge at Tabulam, the Pacific Highway upgrade from Warrell Creek to Nambucca Heads, a BHP and BMA transmission line at Caval Ridge and a shoring wall at Port Macquarie hospital.
These are completed jobs, published years before the administration. They show what kind of business this was: one whose work depends on heavy drilling rigs, skilled operators and difficult ground. Replacing a contractor like that partway through a package can mean new machinery, crews and mobilisation. That is a general point about the trade, not evidence that any project was affected.
Get the Daily Register
Legal names, operating names, ACNs, court dates and process changes, connected in one daily register. Choose the Daily Register, company watches or sector monitoring on the options page.
A council bridge, from the customer's side
Project pages describe work from the contractor's side. Bellingen Shire Council's contracts register for 2021–22 records it from the customer's. It lists LTS Mining & Civil, of Lake Cathie, for the piling on the Tallowwood Point Bridge under the Fixing Country Bridges program, starting on 2 July 2021 after three quotes were received.
The register records the contract at $181,505, with two variations recorded at $208,760 and $28,656. The council reopened the bridge in December 2021.
The Gold Coast connection in 2026
The company's most recent public trail runs to the Gold Coast. Earlier in 2026, an LTS project manager wrote publicly about working on The Landmark at Mermaid Beach for LTS. The Landmark is Aniko Group's four-tower development, reported at $2.5 billion, which broke ground in June 2025 with Aniko's own construction arm as builder. In May 2026, Aniko published a construction update reporting its perimeter retention piling complete.
That establishes a public link between LTS and the project during 2026. It does not establish what LTS's package was, who drilled the piling Aniko reported complete, or whether any LTS work there was unfinished on 13 October. Nothing in the public record connects the administration to the project.
The rigs
Specialist piling depends on large drilling rigs. LTS's 2018 website published the specification sheet for a Soilmec SR-40 rig. In 2024, Soilmec Australia announced that LTS was adding an SR-65 BlueTech rig to its fleet, and in 2026 an advertisement promoted two SR-40 rigs available for wet hire through LTS, meaning with operators.
Using a machine is not the same as owning it. A rig may be owned outright, financed or hired, and a machine advertised for hire is not automatically an asset available to unsecured creditors. Which of LTS's rigs belong to the company, and which are subject to someone else's interest, is a question for the administrators.
Four groups, four different questions
Head contractors need to know whether LTS held any unfinished piling package. A completed job is a different position from one still needing drilling, crews and rigs.
Equipment owners and financiers need to know which machines fall under their agreements and where those machines are.
Suppliers and subcontractors need to confirm that their invoices are addressed to LTS Mining & Civil Pty. Ltd., and not to another entity.
Employees need to know whether the administrators will keep the business trading.
For all four, the company is LTS Mining & Civil Pty. Ltd., ACN 164 598 645, ABN 71 164 598 645. The first creditors' meeting is a virtual meeting at 11am AEDT on 23 October, with proofs and proxies due by 5pm AEDT on 22 October.

What remains unresolved
why the company entered administration
which contracts were still running on 13 October, including any at The Landmark
which rigs the company owns, and which are financed or hired
whether the administrators will keep the business trading
what creditors will be asked to decide
None of those answers is in the appointment notice. The administrators' report to creditors is where they start.
The question is not how much the projects LTS worked on were worth. It is what LTS itself owned, owed and was still contracted to deliver on 13 October.
Watch companies before the headline
Choose the companies or sectors you care about. Administrations, liquidations, court applications and name changes arrive tied to the legal company behind them.
If you are owed money by a company in an insolvency process and are unsure which entity you dealt with: They owe me money
We publish public-record information, not advice. The administrators are the authoritative source on the administration, and nothing here is a statement about any project, contractor or claim.
Sources and records
ASIC notice, LTS Mining & Civil Pty. Ltd., 13 October 2026: the appointment, the appointor, the administrators, the meeting and the proof deadline.
ASIC company register, Australian Business Register and the Queensland Building and Construction Commission licence register: registration, location, licence class and financial category.
LTS Mining & Civil supplier profile on the ICN Gateway: the Yatala premises and the ABN.
LTS project pages as published in 2019: Coopers Gap and Kennedy Energy Park: the transmission-line foundations and the project list.
Bellingen Shire Council contracts register 2021–22 and the council's 6 December 2021 news release on the bridge reopening: the Tallowwood Point Bridge contract and reopening.
Aniko Group breaks ground on The Landmark: the development, its value and its builder.
Aniko Group, May 2026 construction update; LTS project manager's public post; Soilmec Australia's 2024 announcement; the 2026 wet-hire advertisement: the Gold Coast connection and the rigs.